Lien rules

California lien deadlines (2026)

Every California mechanics-lien deadline on one page: preliminary notice, lien filing and enforcement windows, each with the statute citation. Verified 2026-10-13.

Verified 13 Oct 2026 · Legal information, not advice

Every California deadline

RuleWhoWindowClock startsIf missedStatute
Preliminary noticeSubcontractor / Supplier20 daysfrom the first day you furnishRight lostCal. Civ. Code § 8000 et seq.
Lien filingAll claimants90 daysfrom the last day you furnishRight lostCal. Civ. Code § 8000 et seq.
Enforcement (suit)All claimants90 daysfrom the day the lien is recordedRight lostCal. Civ. Code § 8000 et seq.
Acceleration ruleAll claimants30 daysfrom project completionContext onlyCal. Civ. Code 8180-8190

Statute notes

Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.

Never miss a California deadline again

EvoNotice reads your job sheet every morning and tells you which notice or lien window is closing — for California and every other jurisdiction you work in. Every plan includes the 18-document lien pack.

EvoNotice warns; it does not file.

Filing a lien, notice or suit is a separate legal act performed by you or your counsel. The board only computes the date.

Keep reading

Lien deadlines in every jurisdiction

The same board works across state and provincial lines.

57 jurisdictions.

See all 57 →

Start with one source

Never miss a California deadline.

Connect one read-only source and get the board at 7:00.