Every Alaska mechanics-lien deadline on one page: preliminary notice, lien filing and enforcement windows, each with the statute citation. Verified 2026-10-13.
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Preliminary notice | Subcontractor / Supplier | Optional | before you start furnishing | Context only | Alaska Stat. § 34.35.064 |
| Lien filing | All claimants | 120 days | from the last day you furnish | Right lost | Alaska Stat. § 34.35.068 |
| Enforcement (suit) | All claimants | 6 months | from the day the lien is recorded | Right lost | Alaska Stat. § 34.35.080(a) |
| Acceleration rule | All claimants | 15 days | from project completion | Context only | Alaska Stat. § 34.35.068(b) |
Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.
EvoNotice reads your job sheet every morning and tells you which notice or lien window is closing — for Alaska and every other jurisdiction you work in. Every plan includes the 18-document lien pack.
Filing a lien, notice or suit is a separate legal act performed by you or your counsel. The board only computes the date.